Related Articles
Capturing PDRI Action Items
During a Project Definition Rating Index (PDRI) assessment, enter applicable action items by clicking the Action Items button, as shown in the image below. Capture Action Items in Facilitation View Beneath the Action Items button is a table to show ...
Steps to Conduct a PDRI Assessment
To begin, click the Prepare link beside the PDRI Assessment from the Carve Project Dashboard. This will open the PDRI Assessment. Prepare Assessment Link Within the PDRI Assessment, select a PDRI section tab, as shown in the image below. It is ...
PDRI Structure
PDRI assessments are organized into three sections for systematic assessment of the: Basis of project decision - the business objectives and drivers Basis of design - processes and technical information required Execution approach - for executing the ...
PDRI Scores
Each PDRI element is assigned a definition level between 1 (completely defined) to 5 (undefined). Elements that are not applicable are scored 0 and excluded from the total calculation. Each element’s definition level corresponds to a score based on ...
Scoring PDRI Elements
Each PDRI Element is scored on a scale of 0 - 5. 0 - Not Applicable 1 - Complete Definition 2 - Minor Gaps 3 - Some Gaps 4 - Major Gaps 5 - Incomplete or Poor Definition These definition levels can be seen by hovering over each number, as shown in ...