Create Action Items

Create Action Items

Within an assessment, Action Items can be created in the following locations:
  1. Action Items tab
  2. Low Definition tab (Project Definition Rating Index (PDRI))
  3. Missing Factors tab (Construction Readiness Assessment (CRA) and Commissioning & Startup Readiness (CSU))
  4. Element/Factor Facilitation view 
  5. Category dashboards (CRA and CSU)

From the Action Items tab

  1. From the Action Items tab, select Create Action Item.
Create Action Item from Action Items TabCreate Action Item from Action Items Tab
     
      2. Enter the Action Items details. For the following fields:      
  1. Description
  2. Assigned to
  3. Target date
  4. Status (open, closed, cancelled)
  5. Category – what category does the action item pertain to (optional)
  6. Element (PDRI) / Factor (CRA & CSU) – what element or factor does the action item pertain to (optional)
Create Action Item WindowCreate Action Item Window

      3. Click Save.

From the Low Definition tab (PDRI)

Create Action Item from Low Definition Tab (PDRI)Create Action Item from Low Definition Tab (PDRI)

From the Missing Factors tab (CRA and CSU)

Create Action Item from Missing Factors Tab (CRA)Create Action Item from Missing Factors Tab (CRA)

From the PDRI Element facilitation view

  1. Within a PDRI assessment, navigate to one of the PDRI sections:
    1. Basis of Project Decision
    2. Basis of Design
    3. Execution Approach
    4. Accuracy (if applicable)
  2. Click on the appropriate element to open the facilitation view.
  3. Click on the Action items button.
Create Action Item from Facilitation View (PDRI)Create Action Item from Facilitation View (PDRI)

From the Assessment tab (CRA and CSU) 

Category level

Create Action Item from Assessment Tab (CRA)Create Action Item from Assessment Tab (CRA)

Factor level (facilitation view)

Create Action Item from Factor Level Facilitation View (CRA)Create Action Item from Factor Level Facilitation View (CRA)

    • Related Articles

    • Manage Action Items Overview

      Action items are created during the facilitated Project Definition Rating Index (PDRI) Assessment, Construction Readiness Assessment (CRA), or Commissioning & Startup Readiness (CSU) Assessment during the element/factor review or from the Action ...
    • Copy Action Items from Previous Assessment

      Facilitators can update the status of action items and copy action items from a previous assessment to a new assessment (e.g. from Project Definition Rating Index (PDRI)-2 to a PDRI-3 assessment or from Construction Readiness Assessment (CRA) ...
    • Reorder Action Items

      Reordering the list of Action Items can position high-priority activities at the top to assist with prioritization. To reorder action items: From the Carve Project Dashboard, navigate to the correct assessment. Click Prepare. Within the assessment, ...
    • Delete Action Items

      To delete action items from the Action Items tab: From the Carve Project Dashboard, navigate to the correct assessment. Select Prepare. Navigate to the Action Items tab within the assessment. Identify the action item to be deleted and select the down ...
    • Edit Action Items

      To edit an action item from the Action Items tab: On the Carve Project Dashboard, navigate to the correct assessment. Click Prepare to open the assessment. Navigate to the Action Items tab. Click the down arrow beside the action item to be edited. ...