Modifying PDRI Score Ranges and Associated Colours

Modifying PDRI Score Ranges and Associated Colours

It is possible to modify the default colour representing the project score, the numerical range for that colour, and the number of intervals included for each Stage Gate. The default in Carve compares the project score to the Construction Industry Institute (CII) Industry Standard for that particular stage gate.
  
The default colour coding logic for score ranges:
  1. The project is coded green if the score is within or less than the CII recommended range.
  2. The project is coded yellow if the score is is close to the high end of the CII recommended range
  3. The project is coded red if the score is greater than the CII recommended range
To modify the numerical ranges attributed to specific colours:
  1. From the Admin Tab, select PDRI Ranges
  2. From the Template drop-down menu, select the template for which the colour and ranges will be modified. 
  3. To create a new range entry, click the Create range entry button. Chose a Project Gate, the desired score range, and colour (as shown below).  
  4. To modify an existing range, click on the row you wish to modify and the editable row will appear at the top of the screen (below the template selector).  
  5. Click Save.
Notes
Ensure you have ranges that cover all scores between “0” to “1000” inclusive. Changes to the colours will apply to all projects past and future, for the template you have modified.