Modifying PDRI Score Ranges and Associated Colours

Modifying PDRI Score Ranges and Associated Colours

It is possible to modify the default colour representing the project score, the numerical range for that colour, and the number of intervals included for each Stage Gate. The default in Carve compares the project score to the Constrution Industry Institute (CII) Industry Standard for that particular stage gate.
  
By default, the project is coded green if the score is less than the high range of the Industry Standard for that stage gate.  The industry standard is defined by CII.
  1. The project is coded green if the score is within or less than the CII recommended range.
  2. The project is coded red if the score is greater than this value.
To modify the numerical ranges attributed to specific colours:
  1. From the Admin Tab, select PDRI Score Ranges
  2. From the Template drop-down menu, select the template for which the colour and ranges will be modified. 
  3. To create a new range entry, click the Create range entry button. Chose a Project Gate, the desired score range, and colour (as shown below).  
  4. To modify an existing range, click on the row you wish to modify and the editable row will appear at the top of the screen (below the template selector).  
  5. Click Save.
Ensure you have ranges that cover all scores between “0” to “1000” inclusive. Changes to the colours will apply to all projects past and future, for the template you have modified.

Edit Score Ranges and Colours (PDRI)Edit Score Ranges and Colours (PDRI)

    • Related Articles

    • Managing Score Ranges Overview

      Pictorial representations in Carve provide users a quick indication of PDRI, Construction Readiness, and Commissioning & Operational Readiness results and how the current project compares with either industry standards or internal benchmarks. PDRI ...
    • Modifying Construction Readiness (CRA) Score Ranges and Associated Colours

      It is possible to modify the default colour representing the project score and the numerical range for that colour, and the number of intervals included. The default in Carve compares the project score to the Construction Industry Institute (CII) ...
    • Modifying Commissioning & Operational Readiness Score Ranges and Associated Colours

      It is possible to modify the default colour representing the project score and the numerical range for that colour, and the number of intervals included. Admin users can also adjust the category-level target scores for the each Commissioning phase. ...
    • Default Colours and Ranges for PDRI Dashboard

      Carve starts with default colours attributed to ranges of scores for PDRI results. The default ranges and colours are listed in the table below: Industrial, Building, & Infrastructure Templates: Gate Minimum Score Maximum Score Colour PDRI-1 0 800 ...
    • Default Colours and Ranges for Commissioning & Operational Readiness

      The Commissioning templates have default score range colours to serve as a guide to users. As a default, these values are the same for each gate (Commissioning Phase). The default ranges and colours are listed in the table below: Minimum Score ...