Enter Commissioning & Operational Readiness Assessment Attendees
Knowing who attended the Commissioning & Operational Readiness Assessment can provide insight on the final score. For example, if a key project stakeholder was not able to attend the Assessment, it may impact the overall score for their area(s) of expertise. Make not of key stakeholders who were not able to attend the Assessment.
Import Attendees
Please refer to the Import Attendees article for full details on how to upload attendee information through a CSV file.
Add New Attendees
- From the Attendees tab, select Create Attendee.
- On the Create Attendee pop-up enter the following information:
- Name (required)
- Organization – often front-end planning teams include team members from several organizations (e.g. owner, design contractor, consultant)
- Role – enter the attendee’s project role (this may or may not be their their job title at their organization)
- Contact
- Email
- Click Save
Add an Attendee Edit and Delete Attendees
To edit attendee information:
- From the Attendees tab, select the down arrow beside the name of the attendee to be edited.
- Select Edit.
- Update the required fields.
- Click Save.
To delete an attendee:
- From the Attendees tab, select the down arrow beside the name of the attendee to be edited.
- Select Delete.
- Select OK to confirm the deletion.
Related Articles
Steps to Prepare for a Commissioning & Operational Readiness Assessment
Before leading a Commissioning & Operational Readiness Assessment, it is recommended that the facilitator completes the following preparation steps: Search for an existing project in Carve. If an existing project is found, proceed to Step 3. If there ...
Commissioning & Operational Readiness Review Mode
After a Commissioning & Operational Readiness Assessment has been completed, it can be reviewed from the Review Mode. The Assessment Review Mode allows users to view the assessment details in a read-only view. This is the primary view accessible to ...
Commissioning & Operational Readiness Summary Report
From within the assessment, select the Summary tab. The Summary tab contains the following items: Readiness dial. Depending on the Readiness Type selected on the Session Details page, the transition readiness or overall readiness will be displayed. ...
Create a Commissioning & Operational Readiness Assessment
If a new project is being created, the user will be prompted to create the Commissioning & Operational Readiness Assessment at the same time. Refer to the section Create a Project. If the project already exists, Locate the project and click the ...
Enter Commissioning & Operational Readiness Session Details
The default tab of the Assessment dashboard is the Session Details. In the Session Details tab, fill out information for Readiness Type (Select Overall or Transition Readiness from the dropdown menu. This determines the readiness scoring type used ...