Facilitating a Commissioning & Operational Readiness Assessment
Completing Subsequent Commissioning Assessments
Multiple Commissioning & Operational Readiness assessments can be completed within the same project. The facilitation process will differ slightly if this is the first assessment in a particular Commissioning phase or not. To begin, select Create ...
Commissioning Readiness Chart
Depending on the Readiness Type selected on the Session Details tab, 1 of 2 readiness charts will be displayed: Transition Readiness Chart Overall Readiness Chart To change what chart is displayed on this page, the Readiness Type on the Session ...
Commissioning Missing Factors
The Missing Factors tab shows factors answered as No. Users can filter which factors are shown by using the drop-down menu at the top to select between three options: All Missing Factors Hot Spots Ongoing Factors User can also create Action Items and ...
Steps to Conduct a Commissioning & Operational Readiness Assessment
To begin the Commissioning & Operational Readiness Assessment, click the Prepare link beside the Commissioning Assessment from the Carve Project Dashboard. This will open the Commissioning Assessment. Prepare Assessment Link Assessment View Within ...
Capturing Commissioning & Operational Readiness Action Items
During a Commissioning & Operational Readiness Assessment, enter applicable action items by clicking the Action Items button, as shown in the image below. Commissioning Facilitation View - Enter Action Items Beneath the Action Items button is a table ...
Capturing Commissioning & Operational Readiness Comments
During the facilitated Commissioning & Operational Readiness Assessment, record key comments from the project team's discussions in the Comments box. Commissioning Facilitation View, Capture Comments Comments can also be inputted or edited from the ...
Scoring Commissioning & Operational Readiness Factors
Each Commissioning & Operational Readiness factor will be scored as Yes, No, or N/A (Not Applicable). It is recommended that the factor answer be inputted after any applicable comments and action items have been answered. Once a factor answer is ...