Steps to Conduct a PDRI Assessment

Steps to Conduct a PDRI Assessment

To begin, click the Prepare link beside the PDRI Assessment from the Carve Project Dashboard. This will open the PDRI Assessment.

Prepare Assessment LinkPrepare Assessment Link

Within the PDRI Assessment, select a PDRI section tab, as shown in the image below. It is recommended to start with the Basis of Project Decision section, followed by the Basis of Design, and then the Execution Approach. 

Assessment Screen, Section Tabs (PDRI)Assessment Screen, Section Tabs (PDRI)

From within the PDRI section view, click on the name of an element. It is recommended to start with the first element of the section. Clicking on the name of the element will open the facilitation view. Each element contains an element description. This will kick-start your discussion with the project team to assess the definition level of the element.

For each PDRI element, the facilitator/co-facilitator will use Carve to:
  1. Record comments during each element discussion.
  2. Record Action Items. These can be associated with an individual element, or to the project as a whole.
  3. Score each element on a scale from 1-5. Or, of the element is not applicable, score it a 0. Definition level descriptions are included in the PDRI MATRS Industrial 5.0 template to improve scoring consistency. 
    1. If necessary, Carve polling can be use to increase engagement and buy-in while scoring PDRI elements.
After each element has been discussed and scored within a PDRI section, move on to the next section until all sections have been completed. It is important to note that the newer PDRI templates include a fourth section on Accuracy. More details about the Accuracy section are available here

Once all sections have been completed, the facilitator can review the following sections with the project team:
  1. Action Items
  2. Low Definition Elements
  3. PDRI Score and MATRS Score (if applicable)

    • Related Articles

    • Steps to Prepare for a PDRI Assessment

      Carve’s facilitation steps are based on PDRI facilitation best practices from CII. Facilitators can either: Complete the entire facilitation process using Carve Use CII’s PDRI spreadsheet templates to collect assessment data and import into Carve ...
    • Steps to Closeout a PDRI Review

      After a PDRI Assessment has been completed, it is recommended that the facilitator complete the following steps: Create the PDRI Summary Report. This report will communicate the results of the PDRI Assess to all relevant project stakeholders. Publish ...
    • Create a PDRI Assessment

      If a new project is being created, the user will be prompted to create the assessment at the same time. Refer to section Create a Project. To create an assessment in a pre-existing project: 1. Locate the project and click the project name 2. Click ...
    • Enter PDRI Assessment Attendees

      Knowing who attended the PDRI Assessment can provide insight on the PDRI score. For example, if a key project stakeholder was not able to attend the assessment, it may impact the overall score for their area(s) of expertise. Make note of key ...
    • Exclude Elements in the PDRI Assessment

      Elements can be excluded in two ways: at the template level and in a specific assessment. Excluding project components at the template level will remove them from all assessments using that template, while excluding at the assessment level is ...